Hoppa till innehållet
FE
Fermilab
United States·Illinois

Central Utility Building Addition and Renovation Construction, UIP Subproject 1-CUB

Nov 19, 2026·SAM-081a16b3cb52439ea797d5ed0cf3ac6b
Open
Services
Solicitation
20 days left
PublishedDeadline
Nov 19, 2026Dec 17, 2026

Description

On November 19, 2026, Amendment No. 4 was issued to provide responses to questioins received from prospective offerors, Replace Exhibts G, L, and M with Revised Exhibits, provide informational documents, and add additional site visit dates. On Ocotber 30, 2026, Amendment No. 3 was issued to provide responses to questioins received from prospective offerors, provide as-built drawing and photos for reference only, extend thequestions due date to December 1, 2026, and to extend the proposal due date to December 17, 2026. On October 7, 2026, Amendment No. 2 was issued to correct badge access link provided in Amendment No. 1. On October 6, 2026, Amendment No. 1 was issued to provide dates for site visits. This scope of work is to build an addition and renovate the Central Utility Building (CUB). The CUB supplies chilled water, hot water, low conductivity water, and makeup water to various lab buildings and systems. These systems serve both comfort cooling and heating needs, as well as process cooling and utility requirements. It is vital to Fermilab’s mission that CUB be revitalized and expanded, ensuring the ability to serve existing and future loads. The General contractor shall furnish all required supervision, labor, materials, tools, plant and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications. All work includes transportation, overhead, bonding costs, safety oversight, quality control oversight, and supervision as required to construct the project described in the drawings, technical specification and the detailed description contained herein. The critical schedule constraint for construction of this project is Fermilab’s accelerator shutdown, with an anticipated scheduled start on January 1, 2028, and anticipated end date of January 1, 2030- these dates may change depending on the needs of the Lab. The General Contractor must start their on-site efforts, and complete the construction scope under this contract, within the shutdown window. This project includes the following milestones: Milestone 1 – Issuance of Notice to Proceed (NTP) to 30th December 2027. This milestone is intended for completion of necessary submittals and RFIs, approval of shop drawings for fabrication and procurement. Milestone 2 – 3rd January 2028; This milestone marks the point where construction work may begin. Milestone 3 – 31st January 2029; AUP 1 CUB Extension complete. Milestone 4 – 29th June 2029; AUP 2 Existing CUB Upgrade complete. Milestone 5 – 28th September 2029; Completion of CUB- including all remedial work following removal of site trailers.

Tender details

FE

Fermilab

United States

Notice type

Contract notice

Published

Nov 19, 2026

Deadline

Dec 17, 2026

Contract type

Services

Main activity

General public services

Solicitation no.

RFP-376508-CD

NAICS

236210

Contracting office

Batavia, IL

Contact

Documents

More tenders

About the contracting office

Fermilab - DOE Contractor · Department of Energy

Fermilab - DOE Contractor has 16 open solicitations on SAM.gov right now, and 9 of them close within 14 days. 25% are set aside for small business. This notice gives bidders a 28-day response window, with 20 days left.

Most common sectors at this office: Construction (10), Manufacturing (5), Professional, scientific and technical services (1).

All 16 open solicitations from Fermilab - DOE Contractor